目 录 一、工程简介··············································1 二、施工准备··············································1 三、施工工艺流程··········································2 四、施工队人员、机械配备情况······························3 五、施工工艺、工序及要求··································3 六、安全措施··············································6 七、环境保护及文明施工措施································11 附件1:道路标示牌········································13 附件2:某临时便道平面布置图·························16 附件3:某临时便道标准横断面图·······················17
1、总体施工安排 第一次:拆除第二跨和第三跨渡槽施工,在长沙西站和望城车站与施工地点分别设驻站联络员和现场防护员,用对讲机保持3-5分钟联系一次,掌握列车运行情况,利用线路封锁点施工,设停车手信号防护,并按照既有线封锁施工的要求,在距离施工地点两侧各20米得位置设置移动停车信号牌。